Extended Detention: Non-GI

Extended detention holds runoff for gradual release and sediment settling. Although this page is reached through the large-scale library, the practice belongs to non-GI Chapter 11.2. That chapter lists quality and quantity use under a waiver or variance and provides no recharge credit. Manual 11.2, p. 1

Use the main extended-detention page for the complete practice summary.

Capture the full Water Quality Design Storm (WQDS) without overflow. Provide at least 12 hours from maximum storage until 10% remains, using no more than 24 hours in the TSS-removal calculation. The resulting total suspended solids (TSS) credit is 40–60% when the chapter's design criteria are met. Manual 11.2, p. 1 Manual 11.2, p. 3

Keep the larger-storm outlet routing separate from the treatment check. Routing may not count exfiltration as discharge. Manual 11.2, p. 3

For a surface extended-detention basin, keep the bottom at least 1 ft above seasonal high water table (SHWT), excluding low-flow channels; those channels must be at or above SHWT. For a subsurface basin, the lowest extent, including pipes and bedding, must be at least 1 ft above SHWT. Manual 11.2, p. 3

Inspect structures annually. Inspect sediment- and debris-catching components at least twice a year and after storms exceeding 1 inch. Keep outlets and maintenance access clear, and remove sediment when the basin is dry where practicable. Manual 11.2, p. 13

Record the design drain time and compare it with actual performance. Check the outlet, underdrain where present, groundwater and tailwater if drawdown changes. Failure to fully drain within 72 hours requires corrective action and a maintenance-plan revision. Manual 11.2, p. 14

Detention is classified as GI or recharge. Chapter 11.2 expressly excludes those uses. Soil testing establishes groundwater conditions; it does not change the practice's classification. Manual 11.2, p. 1 Manual 11.2, p. 3

Drawdown changes after construction. Check accumulated sediment, outlet obstruction and downstream water levels against the design. Manual 11.2, p. 13 Manual 11.2, p. 14

Source chapters: January 2026 · Earlier collection. Check the date printed on the chapter when comparing editions.

N.J.A.C. 7:8-5.3 sets the GI selection requirements and exceptions; N.J.A.C. 7:8-5.8 covers maintenance plans for major development.