Skip to content

Volumetric Reduction Credit

Volumetric reduction addresses the runoff from the Water Quality Design Storm (WQDS). January 2026 adds this performance standard in N.J.A.C. 7:8-5.6(d); BMP Manual Chapter 14 explains the design methods. N.J.A.C. 7:8-5.6(d), Jan. 2026, p. 42 BMP Manual 14, p. 1

Regulatory Summary

The starting requirement is WQDS retention through GI BMPs in Tables 5-1 and 5-2. Retention means infiltration, evapotranspiration or reuse without direct or indirect discharge of that runoff to surface waters or treatment works. N.J.A.C. 7:8-5.6(d)1, Sept. 2026, p. 40 N.J.A.C. 7:8-1.2, Sept. 2026, p. 8

Qualifying hydrograph alternative

If the applicant demonstrates technical impracticability under §4.6(a)1, or the runoff is subject to the recharge prohibitions in §5.4(b)3, the site must instead meet both conditions:

Measure Required comparison with the reference
WQDS peak flow Less than the reference peak
WQDS hydrograph duration Greater than the reference duration

The reference uses a drainage area equal to the major development's disturbed area, woods in good hydrologic condition and Hydrologic Soil Group D. Duration starts when flow becomes greater than zero and ends when it returns to zero. Equality fails either strict comparison. N.J.A.C. 7:8-5.6(d)1i, Sept. 2026, p. 40

Offsite alternatives

Section 5.6(d)2 allows all or part of the standard to be met by removing existing impervious surface, retaining WQDS runoff offsite, or combining them. The removal area must equal or exceed the impervious area in the disturbed portions of the development; offsite retention must provide the equivalent or greater required WQDS runoff volume. Retention from other storms does not count. N.J.A.C. 7:8-5.6(d)2i, Sept. 2026, p. 41

Use the same HUC14. A public transportation entity that demonstrates technical impracticability within that HUC14 must provide the reduction within the same Watershed Management Area, as close as practicable. Offsite applications need enough design information and owner permission for joint review and approval; otherwise they are incomplete. Construct the offsite work before or concurrently with the development. N.J.A.C. 7:8-5.6(d)2ii–iii, Sept. 2026, p. 41

The narrow §5.6(d)3 exception covers a public transportation project that qualifies as major development solely because it increases the capacity of an existing stormwater conveyance system. N.J.A.C. 7:8-5.6(d)3, Sept. 2026, p. 41

Engineering Interpretation

Select the route and show its calculation. Technical impracticability must be supported by engineering, environmental or safety reasons for the affected standard and drainage area. Identify soil, groundwater or runoff-source conditions that support the proposed alternative. N.J.A.C. 7:8-4.6(a)1, Sept. 2026, p. 25 BMP Manual 14, p. 3

For beneficial reuse, Chapter 14 specifies that WQDS runoff from the disturbed area be used on site within three days. Check actual reuse demand separately from the cistern's ability to move water out of its primary tank: Chapter 9.1 permits secondary storage, but that transfer alone does not establish the three-day reuse described in Chapter 14. BMP Manual 14, p. 3 BMP Manual 9.1, p. 4

A treatment train can combine retention with a justified hydrograph-control approach for the portions where retention is impracticable or prohibited. Show the volumes and hydrographs for those portions and how the measures work together. BMP Manual 14, p. 3

What Changed in 2026

The July 2023 quantity section ends at §5.6(c); January adds §5.6(d). Infiltration, roof retention and reuse practices already existed, so the new item is the performance standard. Use the edition guide to determine whether it applies to the project. N.J.A.C. 7:8-5.6, July 2023, p. 43 N.J.A.C. 7:8-5.6(d), Jan. 2026, p. 42 BMP Manual 9.1, p. 1

BMP Implications

For retention, Chapter 14 identifies infiltrating practices such as dry wells, bioretention and infiltration basins, plus green roofs, cisterns and GI wet ponds for evapotranspiration or reuse. BMP Manual 14, p. 2

For the qualifying hydrograph route, it lists grass swales, underdrained bioretention and pervious paving, vegetative filter strips and constructed wetlands, among other examples. Demonstrate the required lower peak and longer duration for the selected design; these examples do not grant recharge credit. BMP Manual 14, p. 3 N.J.A.C. 7:8-5.6(d)1i, Sept. 2026, p. 40

Cross References

Regulatory Explorer