Infiltration Feasibility¶
Concept Explanation¶
Infiltration feasibility brings together the runoff source, soil, groundwater, available area and proposed BMP configuration. A favorable soil rate is one part of that decision. Chapter 12 defines infiltration BMPs by their reliance on subsoil infiltration for recharge, quality or quantity performance. Manual 12, Mar. 2024, p. 14
Engineering Evaluation¶
Work through the site evidence¶
| Check | Evidence needed |
|---|---|
| Runoff source | Determine whether §5.4(b)3 prohibits recharge, including high-pollutant-loading stormwater or the specified industrial runoff exposed to source material. |
| Configuration and objective | Identify infiltration, underdrain, liner and overflow arrangements, then select the table route for the intended credit. |
| Soil and groundwater | Obtain the required conductivity tests and SHWT determination at the BMP location; use the correct exploration depth and separation surface. |
| Hydraulic impacts | Assess the temporary groundwater mound, BMP drainage and nearby structures or other infiltration facilities. |
| Space and drainage | Check contributory area, infiltration footprint, storage volume and actual runoff routing. |
The source prohibition and hydraulic assessment are separate requirements. Pretreatment does not override a prohibition under §5.4(b)3. Artesian groundwater prevents use of an infiltration BMP at that location. N.J.A.C. 7:8-5.4(b)3, Sept. 2026, p. 36 N.J.A.C. 7:8-5.2(h), Sept. 2026, p. 31 Manual 12, Mar. 2024, p. 14 Manual 12, Mar. 2024, p. 19
Use the soil-testing, SHWT, mounding and drainage-area pages to assemble that evidence. Construction protection and post-construction verification are also part of demonstrating that the installed BMP works as designed. Manual 12, Mar. 2024, p. 28 Manual 12, Mar. 2024, p. 29
January 2026 volumetric-reduction alternatives¶
Establish the applicable rule edition. In the 2026 volumetric standard, the hydrograph alternative requires demonstrated technical impracticability under §4.6(a)1 or runoff subject to §5.4(b)3. Poor conductivity or high groundwater can support the engineering evidence; they do not automatically remove the standard. N.J.A.C. 7:8-4.6(a)1, Sept. 2026, p. 25 N.J.A.C. 7:8-5.6(d)1, Sept. 2026, p. 40 Manual 14, Jan. 2026, p. 3
For that alternative, the postconstruction WQDS peak must be less than and its zero-to-zero hydrograph duration greater than the reference for an area equal to the proposed disturbance, wooded in good hydrologic condition on HSG D. Equality fails either comparison. Offsite alternatives and the narrow public-transportation exception have separate conditions. N.J.A.C. 7:8-5.6(d)1i, Sept. 2026, p. 40 N.J.A.C. 7:8-5.6(d)2–3, Sept. 2026, p. 41
Affected BMPs¶
- dry wells: use the clean-roof runoff source and native-soil infiltration criteria. Manual 9.2, Jan. 2026, p. 1
- bioretention, including rain gardens and tree pits: distinguish infiltration from underdrained treatment. The underdrained design cannot claim exfiltration in quantity routing. Manual 9.7, Jan. 2026, p. 14 N.J.A.C. 7:8-5.2(f), Sept. 2026, p. 29
- pervious paving: only the subsoil-infiltrating configuration has recharge credit; the underdrained system has separate separation and routing requirements. Manual 9.6, Jan. 2026, p. 3 Manual 9.6, Jan. 2026, p. 11
- small infiltration basins, larger infiltration layouts, small sand filters and large sand filters: demonstrate site infiltration and hydraulic performance, then apply the selection conditions for the scale and objective. Manual 12, Mar. 2024, p. 14 N.J.A.C. 7:8-5.2(f), Sept. 2026, p. 29 N.J.A.C. 7:8-5.2(f), Sept. 2026, p. 30 N.J.A.C. 7:8-5.3, Sept. 2026, p. 33
Where infiltration is unsuitable, compare approved alternatives against the specific unmet standards. A detention or underdrained design may control a hydrograph without providing groundwater recharge or retaining all WQDS runoff. N.J.A.C. 7:8-5.2(f), Sept. 2026, p. 29 N.J.A.C. 7:8-5.2(f), Sept. 2026, p. 30 Manual 14, Jan. 2026, p. 3