Phase 3 - Master 2026 Synthesis: Subsurface Engineering, Volumetric Reduction, and Manual Reorganization¶
Source Documents: - 2023: N.J.A.C. 7:8 (July 2023), BMP Chapter 12, BMP Chapter 13, GI Requirement Fact Sheet - 2026: N.J.A.C. 7:8 (January 2026), BMP Chapter 12, BMP Chapter 13, BMP Chapter 14, GI Requirement Fact Sheet
This report compares the stored July-era and January 2026 collections. Use each PDF's printed revision date: some chapters were retained unchanged. Project applicability, including the later September 2026 amendment, is explained in the rules comparison. Both Chapter 12 copies are printed March 2024; their agreement does not establish the exact July 2023 historical text.
Overview¶
Chapter 12 establishes the subsurface investigation needed to select and design a BMP. Chapter 13 addresses the hydraulic impacts of infiltration on groundwater. January 2026 adds the volumetric-reduction obligation in N.J.A.C. 7:8-5.6(d) and Chapter 14, which explains its retention and alternative compliance pathways. These checks serve different purposes and each applicable obligation must be satisfied.
Soil Testing and Subsurface Evaluation¶
Purpose and supervision¶
Chapter 12 addresses five investigation needs: Hydrologic Soil Group, soil series for recharge calculations, seasonal high water table (SHWT), hydraulic conductivity for design and as-built testing, and groundwater-mounding inputs. Confirm subsurface conditions at the proposed BMP location. Planning-level soil mapping alone does not establish infiltration feasibility. Soil profile pits, borings, hydraulic-conductivity tests and associated documentation must be conducted under the direct supervision of a licensed New Jersey professional engineer. Chapter 12, pp. 1–2.
Establishing seasonal high water table¶
Where redoximorphic mottling is present, use its highest elevation unless the observed water table is higher. Without those indicators, direct observation in pits or borings normally occurs January through April; the Department may adjust that period for climatic conditions. In tidal areas, use the highest applicable water level.
During May through December, when redoximorphic indicators are absent, the soil-survey alternative requires the observed soil-profile morphology to match the detailed mapped soil-series description. Use the highest SHWT in the applicable range. If that verification cannot be made, SHWT remains undetermined and further investigation is necessary. These are conditional alternatives, not interchangeable choices of a convenient water-table value. Chapter 12, pp. 12–13.
Infiltration BMPs need both conductivity and SHWT investigation. Some non-infiltrating configurations also need SHWT information to demonstrate the chapter-specific groundwater separation. Measure from the surface specified for that configuration, such as basin bottom, soil-bed bottom or gravel-layer bottom. Chapter 12, pp. 14–18; SHWT and configuration-specific separation.
Number and placement of explorations¶
The investigation tables distinguish infiltration BMPs, small practices, linear practices, and groups in the same soil mapping unit. For the standard infiltration-area schedule, provide at least two soil profile pits and one additional pit for each additional 10,000 square feet beyond the first 10,000 square feet, with at least one conductivity test per pit. Apply the table's location, area and additional-investigation conditions.
The chapter examples include two pits for a 9,000-square-foot infiltration basin, four for a 25,450-square-foot infiltration basin, and five for a 35,000-square-foot porous paving system. The ten 400-square-foot rain gardens example uses one shared profile pit and one boring per BMP only with its same-soil-mapping-unit and placement conditions. It is not permission to share one investigation across unrelated soils or BMP locations. Chapter 12, pp. 15–18.
Both supplied Chapter 12 documents are printed March 2024. Their testing framework is the same, but those copies do not establish the exact chapter available in July 2023. Earlier collection copy; January collection copy.
Groundwater Mounding Analysis¶
When the analysis is required¶
Whenever stormwater management includes infiltration into subsoil, assess hydraulic impacts under N.J.A.C. 7:8-5.2(h). Consider surficial ponding, basement flooding, interference with sewage-disposal systems and other subsurface structures, and interference with the BMP itself. Static groundwater separation alone does not establish acceptable hydraulic impacts. January rule, §5.2(h), p. 33; Chapter 13, pp. 1–2.
The requirement does not depend on a separate universal threshold of 10,000 square feet of tributary area, 3,000 square feet of BMP footprint, four feet of groundwater separation or mapped Sole Source Aquifer status. Apply the infiltration requirement and the actual site conditions.
Model inputs and design iteration¶
Chapter 13 uses the Hantush Spreadsheet developed by USGS in cooperation with the Department. Its inputs include:
| Input | Chapter 13 approach |
|---|---|
| Recharge rate, R | Governing vertical hydraulic conductivity below the infiltration BMP, reduced by a factor of safety of 2; initial rate no greater than 10 in/hr |
| Infiltration duration | Runoff volume × 12 ÷ (infiltration area × R), with compatible ft³, ft² and in/hr units; no greater than 72 hours |
| Specific yield | Default 0.15; a higher tested value may be used up to 0.2 |
| Horizontal hydraulic conductivity | Default 5R in the Coastal Plain and R outside it |
If the calculated duration exceeds 72 hours, resolve the design; do not truncate a longer computed duration to 72 hours in the model. If the calculated mound reaches the BMP bottom, reduce the assumed recharge rate, adjust duration proportionally and repeat the analysis. Redesign or relocate the BMP where adverse hydraulic impacts remain. Document methods, inputs and assumptions. Chapter 13, pp. 4–5.
These model defaults and the iteration process are retained in both Chapter 13 copies. The BMP-specific chapters also direct designers to Chapters 12 and 13 for soil investigation and hydraulic-impact assessment. Earlier Chapter 13; January Chapter 13.
Volumetric Reduction: New Rule Obligation and Chapter 14¶
The July 2023 rule has no §5.6(d), and the earlier manual has no Chapter 14. January 2026 introduces both. Existing GI, recharge and quantity requirements still apply alongside the new obligation. July rule, §5.6; January rule, §5.6(d), pp. 42–43.
Retention and hydrograph alternatives¶
The primary route retains the Water Quality Design Storm runoff from the applicable impervious area. Chapter 14 describes infiltration through dry wells, bioretention, infiltration basins, pervious paving and sand filters, as well as evapotranspiration and beneficial reuse through green roofs, cisterns and GI wet ponds. A practice name alone does not demonstrate the required retained volume.
Where onsite retention is technically impracticable or infiltration is prohibited under the rule's specified conditions, compare the post-construction WQDS hydrograph with an equal area of disturbed land in woods in good condition on HSG D soil. The peak must be strictly lower and the duration strictly longer. Measure duration from the point where flow first exceeds zero until it returns to zero; equality fails either comparison.
Chapter 14 identifies practices that may provide this alternative performance, including grass swales, underdrained bioretention, underdrained pervious paving, underdrained sand filters, vegetative filter strips and standard constructed wetlands. Demonstrate the required hydrograph performance and the conditions allowing the alternative. Chapter 14, pp. 1–3; January §5.6(d), pp. 42–43.
Impervious removal, offsite work and the transportation exception¶
The rule permits specified impervious-surface removal and offsite retention of equivalent or greater WQDS runoff volume. Apply the same-HUC14 location requirement and the conditioned Watershed Management Area fallback for a public transportation entity where same-HUC14 compliance is technically impracticable. Offsite work must be fully reviewable and constructed before or concurrently with the major development.
The narrow exception applies to a project undertaken by a public transportation entity that meets the major-development definition solely because it increases the capacity of an existing stormwater conveyance system. It does not exempt public transportation work generally. January §5.6(d), pp. 42–43.
Using the Chapters Together¶
- Establish the governing rule edition and review program, including application and approval history.
- Use Chapter 12 to establish site-specific soil and groundwater conditions.
- Apply the selected BMP chapter's configuration, testing, separation, permeability and drainage requirements.
- Use Chapter 13 to assess hydraulic impacts wherever the design infiltrates into subsoil.
- Demonstrate each applicable recharge, runoff-quality, runoff-quantity and volumetric-reduction standard separately.
The GI fact sheets retain their emphasis on distributed practices, runoff management close to its source and applicable contributory drainage-area limits. Chapter 14 adds a dedicated explanation of volumetric reduction; it does not replace the soil investigation, hydraulic-impact or BMP-specific design checks. Earlier GI fact sheet; January GI fact sheet.