Large-Scale Sand Filter

A large-scale sand filter captures runoff, filters it through sand and infiltrates the treated water into subsoil. Chapter 10.3 covers this GI arrangement. Its summary lists 80% total suspended solids (TSS) removal and recharge under a waiver or variance, with quantity control available for on-line systems. Manual 10.3, p. 1

An underdrained sand filter is a different, non-GI practice covered by Chapter 11.4. Manual 10.3, p. 3

Capture the full Water Quality Design Storm (WQDS) runoff without overflow. Provide at least 18 in of sand and no more than 24 in of WQDS ponding above it. The sand-bed design permeability is capped at 2 in/hr; when using that rate, use a 36-hour design drain time. Manual 10.3, p. 6 Manual 10.3, p. 7

Pretreatment is required. The review agency may waive roof-runoff pretreatment only after checking that debris is not expected, including from mature surrounding trees. A forebay helps maintenance but has no adopted TSS-removal credit of its own. Manual 10.3, p. 5

Standing water must drain within 72 hours. Exfiltration may not be used in routing calculations. If optional turf cover is used, its topsoil permeability must be twice the subsoil design permeability. Manual 10.3, p. 7 Manual 10.3, p. 16

Keep seasonal high water table (SHWT) and bedrock at least 2 ft below the sand-layer bottom. Do not construct the filter where surrounding slopes are 15% or greater. Make the infiltration area as level as possible and test the receiving soils. Manual 10.3, p. 6 Manual 10.3, p. 7

Evaluate groundwater effects and the quality of water being infiltrated. Chapter 10.3 identifies restrictions for high-pollutant-loading areas and runoff exposed to source material, along with nearby wells, sewage-disposal systems and sensitive receiving areas. Manual 10.3, p. 16

Inspect structural components annually. Inspect sediment- and debris-catching components at least twice a year and after storms exceeding 1 inch. Keep pretreatment and access usable so sediment can be removed before it reaches the sand. Manual 10.3, p. 16

Investigate a significant change in drain time. If the WQDS does not drain within 72 hours, corrective action is required and may include replacing upper sand layers. Include the expected replacement frequency in the maintenance manual. Manual 10.3, p. 18

Sediment reaches the sand. Neglected pretreatment can seal the surface and reduce drainage. Inspect upstream capture and restore media permeability as needed. Manual 10.3, p. 5 Manual 10.3, p. 18

Exfiltration is credited in the wrong model. This chapter expressly prohibits exfiltration in routing, even though the practice physically infiltrates after a storm. Keep the drainage check and peak-flow routing calculation distinct. Manual 10.3, p. 7

Source chapters: January 2026 · Earlier collection. Check the date printed on the chapter when comparing editions.

N.J.A.C. 7:8-5.3 sets the GI selection requirements and exceptions; N.J.A.C. 7:8-5.8 covers maintenance plans for major development.

Chapter 10: large-scale GI · BMP Library