Skip to content

Green Infrastructure Requirement

Green infrastructure (GI) manages runoff close to its source through infiltration into subsoil, filtration by vegetation or soil, or storage for reuse. These are the three functions in the rule's definition. N.J.A.C. 7:8-1.2, Sept. 2026, p. 5

Regulatory Summary

Choose a BMP table for the performance standard being addressed. The ordinary routes in N.J.A.C. 7:8-5.3 are: N.J.A.C. 7:8-5.3(b)–(d), Sept. 2026, p. 33

Design objective or approval Selection route
Recharge and water quality Table 5-1 and/or an alternative approved under §5.2(g)
Quantity Table 5-1 or 5-2 and/or an approved alternative
Granted variance or waiver under §5.3(d) Tables 5-1, 5-2 or 5-3 and/or an approved alternative

The table entries and footnotes identify the credits available for each configuration. For example, underdrained bioretention does not receive recharge credit, and a GI wet pond needs the specified native shoreline buffer and beneficial reuse. N.J.A.C. 7:8-5.2(f), Sept. 2026, p. 29 N.J.A.C. 7:8-5.2(f), Sept. 2026, p. 30

Public transportation projects

Sections 5.3(f)–(j) provide a conditional route for public roadway and railroad projects. Investigate Table 5-1/5-2 GI within the project limits, then disturbed land immediately adjacent to them. For unmet recharge and quality standards, the rule also requires the specified investigation of upstream land in the same HUC14. N.J.A.C. 7:8-5.3(f)–(g), Sept. 2026, p. 34 N.J.A.C. 7:8-5.3(g), Sept. 2026, p. 35

After those demonstrations, §5.3(g)3 allows Table 5-3 measures for the standards that cannot be met because of unsuitable hydrologic, hydraulic or physical conditions, without the §5.2(e) waiver. Submit the supporting investigations and engineer/executive certifications required by §5.3(i)–(j). Further waiver requirements and the bar on waivers for new public roadways or railroads remain in §5.3(h). N.J.A.C. 7:8-5.3(g)–(j), Sept. 2026, p. 35 N.J.A.C. 7:8-5.3(j), Sept. 2026, p. 36

Engineering Interpretation

Check drainage area and configuration

Table 5-1 practice Maximum contributory drainage area
Dry well 1 acre
GI manufactured treatment device 2.5 acres
Small-scale bioretention, infiltration basin or sand filter 2.5 acres
Pervious paving Additional inflow area may not exceed three times the paving area

Apply these limits to the actual drainage layout. “Contributory drainage area” excludes the BMP's own footprint. Approved alternative measures have the additional GI, drainage-area and review requirements in §5.2(g). N.J.A.C. 7:8-1.2, Sept. 2026, p. 3 N.J.A.C. 7:8-5.3(b), Sept. 2026, p. 33 N.J.A.C. 7:8-5.2(g), Sept. 2026, p. 31

Variances

The municipal variance process in §4.6 requires technical impracticability, maximum possible compliance on site and qualifying mitigation. Technical impracticability means engineering, environmental or safety reasons, demonstrated for the affected drainage area and standard. N.J.A.C. 7:8-4.6(a), Sept. 2026, p. 25

The Department's §5.10 process requires the specified report from each MS4 permittee with post-construction review obligations, offsite mitigation, and the Department's no-adverse-impact determination. Municipal approval and design consistency are required where the project is subject to municipal approval. The rule also contains a specific transportation mitigation provision. Submit proof of completed mitigation within 30 calendar days of its completion. N.J.A.C. 7:8-5.10, Sept. 2026, p. 46

What Changed in 2026

The GI definition and basic table routes already existed in July 2023. January adds the conditional transportation route and the Department variance section. It also introduces volumetric reduction in §5.6(d). Evaluate that standard separately from a practice's GI classification. N.J.A.C. 7:8-1.2, July 2023, p. 6 N.J.A.C. 7:8-5.3, July 2023, p. 37 N.J.A.C. 7:8-5.3, Jan. 2026, p. 35 N.J.A.C. 7:8-5.10, Jan. 2026, p. 48

BMP Implications

Use the practice's design chapter after selecting its legal route:

Their GI label does not give every practice recharge, quality and quantity credit. Use the individual table entries and manual criteria. N.J.A.C. 7:8-5.2(f), Sept. 2026, p. 29 BMP Manual 9.7, p. 1 BMP Manual 9.6, p. 1

Where the volumetric hydrograph alternative is justified, demonstrate both a peak below and a duration above the specified woods/good/HSG-D reference. The volumetric-reduction page covers its offsite alternatives and limited transportation exception. N.J.A.C. 7:8-5.6(d), Sept. 2026, p. 40 N.J.A.C. 7:8-5.6(d), Sept. 2026, p. 41

Cross References

Regulatory Explorer